The final wind turbine at the 920 MW Greater Changhua 2b and 4 offshore wind farms in Taiwan was installed last week, completing a main phase of construction. The Greater Changhua 2b and 4 projects are located 35–60 km off the coast of Changhua County and include 66 SG 14-236 wind turbines, each with a capacity of 14 MW.
Offshore construction of the project began in February 2025, with turbine installation starting in April 2025. The installation work was carried out by Siemens Gamesa using Cadeler’s Wind Maker installation vessel. Greater Changhua 2b and 4 supply electricity under a long-term power purchase agreement signed in 2020. Since first power was generated in July 2025, the projects have been delivering electricity to Taiwan’s power grid. The project is now progressing with turbine commissioning, electrical system testing and completion of cable installation. Greater Changhua 2b and 4 are expected to be fully commissioned in the third quarter of 2026.




