SmartestEnergy has agreed two 20-year, Contract for Difference (CfD)-backed route-to-market Power Purchase Agreements (PPAs) with a joint venture between RWE and KKR for the Norfolk Vanguard West and Norfolk Vanguard East offshore wind projects in the UK.
Located 50 to 80 kilometres off the Norfolk coast in East Anglia, the two projects will each have an installed capacity of approximately 1.4 GW, giving a combined capacity of around 2.8 GW.
Preparatory work for offshore construction is well advanced, with installation work scheduled to begin in early 2027. The first foundations for Norfolk Vanguard West are planned for the first half of 2027, followed by those for Norfolk Vanguard East. Both projects are expected to be fully commissioned in 2030.
SmartestEnergy has contracted for 25% of the combined output of the two projects. The agreements are supported by SmartestEnergy's parent company, Marubeni.