OranjeWind, the joint venture between RWE and TotalEnergies, has signed a Port & Agency Services agreement with Clarkson Port Services for the construction and commissioning phase of the OranjeWind offshore wind farm in the Netherlands.
Clarksons will provide port call and agency services at Den Helder, Rotterdam and Eemshaven, supporting the transport of equipment, materials, personnel and other project requirements in line with applicable regulations. Rotterdam will be used for monopile and secondary steel loadouts, while turbine components will be loaded out from Eemshaven. Den Helder will serve as the marshalling port for bi-weekly service operation vessel and crew transfer vessel calls.
The 795 MW OranjeWind project will be located approximately 53 kilometres west of IJmuiden in the Dutch North Sea exclusive economic zone. Once completed, the wind farm will comprise 53 wind turbines with a capacity of 15 MW each, installed on TP-less monopile foundations.