SSE has submitted a planning application to the Department for Infrastructure for the proposed Tattymoyle Wind Farm in County Tyrone. The application follows environmental assessments and two rounds of public consultation carried out since autumn 2024 with local communities in Omagh, Fivemiletown and the wider south Tyrone area.
The proposed wind farm would be located around 6.5 km south west of Fintona and would include up to ten turbines, each with a maximum tip height of 180 metres. The project is expected to have an installed capacity of around 60 MW.
Subject to receiving planning consent, the delivery and construction of the Tattymoyle Wind Farm would proceed in line with grid availability and other regulatory requirements.