Vestas has announced two orders totalling 614 MW for wind farms in Western Australia. The orders are included in the company’s third-quarter 2026 order intake. The orders for the Parron Maam Marang and Kondinin wind farms cover 99 V162-6.2 MW EnVentus turbines.
For the 484 MW Parron Maam Marang Wind Farm, Vestas will supply 78 V162-6.2 MW turbines for Atmos Renewables. Delivery is planned for 2027, with commissioning scheduled for 2028.
For the 130 MW Kondinin Wind Farm, Vestas will supply 21 V162-6.2 MW turbines for Foresight Group. Delivery is planned for 2027, with commissioning scheduled for 2028.
Both orders include service agreements covering 30 years.